Partington Gasworks

From Graces Guide

Following WWI, the Manchester Corporation Gas Department had a choice of rebuilding the Gaythorn Gasworks or finding a new site outside the city for a new gasworks.

A very large site of 175 acres far outside the City Boundary at Partington in Cheshire was chosen. The first action was to build a gasholder with a capacity of 5mcf.

1929 Most of the new gasworks was built south of the railway line; the first Glover-West CVRs were commissioned; the site also operated Drakes HR. On opening of the Partington gasworks, the Gaythorn gasworks in Manchester closed.

1930s The gas demand in Manchester declined so no new plant was added at Partington.

1945 a Humphreys and Glasgow CWG plant was ordered

1949 The new CWG plant was commissioned; in the same year the Manchester Gas Committee ordered a new Woodall-Duckham vertical retort house, which commissioned in November 1953.

1949 The gasworks were vested in the North Western Gas Board

A supply of refinery tail gas was taken from the nearby refinery of Petrochemicals Ltd. and used to enrich the water gas.

The gas making capacity was much increased by North Western Gas; the Gas Council also added an LNG storage facility.

1955 Following a study by NWGB, the Gas Council decided to build an oil hydrogenation plant.

Additional rail sidings were built to receive butane by rail.

Three large PFD 'Warehouse Tanks' were built to the South East of the main site, a feedstock pipeline delivered naphtha (PFD) from Ellesmere Port. Four LNG tanks, with provision for a fifth, were built south of the railway. The oil-based reformer plant comprised of Power Gas HP CCR, H&G HP CCR, Onia-Geigy (sic) LP Cyclic reformer and an HTR LP Cyclic reforming plant.

1970 the coal gas plants were shut down.

1975 the production of gas at Partington ceased, although the LPG/Air and SNG plants remained available into the natural gas era.