De Dion Bouton (1907)
See also De Dion-Bouton
1907 The De Dion-Bouton company was incorporated in the UK as De Dion-Bouton (1907) Ltd . Directors were Selwyn Edge (Chairman), John William Stocks (MD), Herbert Osbaldeston Duncan (MD in France), S. Van Der Bergh, W. Scott-Leafe and Arthur I. Phillips.
1908-1918 Annual reports in Coventry Archives[1]
1914 'The De Dion Bouton Coachbuilding and Engineering Works.
De Dion Bouton (1907), Limited, of
10, Great Marlborough-street, W., has recently erected
an engineering and coachbuilding works at Hendon.
The engineering works will deal with the company’s
repairs and overhauls, and will take over the work previously carried on at the De Dion repair shops in
Islington. The coachbuilding works form, however, a
new venture for the English De Dion Company. In
addition to the building and renovation of bodies for
De Dion cars the works will be prepared to deal with
work of this class from outside. The new establishment
is situated on the Edgware-road between Cricklewood
and Hendon, and 4 3/4 miles from the Marble Arch. The
site has a frontage of 170 ft., and the depth from the
main road to the rear is 235 ft. The engineering and bodybuilding works are each housed in a one-storey building.
The two buildings are side by side, and are joined by fireproof doors, but to all intents and purposes the two buildings
form separate works. The offices are situated in front,
looking on to a fine court 65 ft. deep. The engineering
shop contains a complete installation of electrically-driven
machine tools, vice-benches, &c., and has 182 ft. of inspection-pits, fitted with plugs for supplying current to electric hand-lamps. The coachbuilding works contains woodworking machinery, smiths’ fires, &c. A high class of
body only is built, and the greater part of the work is
done by hand. Upholstering, painting, varnishing, and
all work necessary for the completion of the bodies is
carried out in the shops. The buildings were finished last
November, and were fully equipped by the end of the
year. The whole of the work from the marking out of
the site was completed in twenty weeks.'[2]