Grace's Guide To British Industrial History

Registered UK Charity (No. 1154342)

Grace's Guide is the leading source of historical information on industry and manufacturing in Britain. This web publication contains 174,136 pages of information and 250,321 images on early companies, their products and the people who designed and built them.

Grace's Guide is the leading source of historical information on industry and manufacturing in Britain. This web publication contains 147,919 pages of information and 233,587 images on early companies, their products and the people who designed and built them.

Clarence Dock Power Station

From Graces Guide
1931. Metropolitan-Vickers alternator rotor
Turbine Hall

The station comprised a low pressure station (No. 1) and a later high pressure station (No. 2). Steam conditions: No. 1 Station: 450 psi and 775 °F (31.0 bar and 413 °C); No. 2 Station: 630 psi and 825 °F (43.45 bar and 441 °C). Typical thermal efficiency: No. 1: Approx 19-20%; No.2: 23-24%. [1]

1928 It was decided by the Corporation to make an investment in a new power station at Clarence Dock; it would initially have two 50MW alternator sets, with ultimate potential for 400MW[2]

1928 Selected as one of 2 new stations to be built under the North-West England and North Wales Electricity Scheme

1929 Construction began on the filled-in basin of Clarence Dock, one of the Liverpool Docks

1931 First generation of electricity. The station was built primarily to operate as a base load station on the national grid. The designed ultimate capacity of the plant was 400,000 kW.

1931 Detailed description of coal handling plant[3] and ash-handling plant[4]. The boiler feed pumps, feed heating system, circulating water system and condensers were described in Engineering 1931/10/02. The Metropolitan-Vickers main transformers were described in Engineering 1931/10/30.

The turbine alternators were described in Engineering 1931/10/23: 'Each of the two main generating sets, which were constructed by Messrs. Metropolitan-Vickers Electrical Company, Limited, Trafford Park, Manchester, comprises a 51,250-kw. two-cylinder turbine, which will be supplied with steam at a pressure of 400 lb. per square inch and a temperature of 725 deg. F. The operating conditions therefore mark a distinct advance on those employed at Lister Drive No. 3, where the steam pressure and temperature are 275 lb. per square inch and 675 deg. F., respectively, while owing to the use of river water at 58 deg. F., instead of a cooling tower giving water at 83 deg. F., it will be possible to increase the vacuum from 27.6 in. to 29 in. of mercury. Each turbine, which runs at 1,500 r.p.m., is coupled to a three-phase alternator, which has an output of 71,500 kv.-a. at a pressure of 7,250 volts and frequency of 50 cycles, while on the same shaft is a 1,562.5 kv.-a. auxiliary alternator, which generates three-phase current at 400 volts, a double exciter, which serves both alternators, and, finally, a permanent-magnet exciter. .... In accordance with recent practice, the stator frame, ... is of welded-steel construction, thus enabling a saving in weight of about 16 tons to be obtained, as compared with a cast frame. The core laminations of the best low-loss transformer iron, containing 4 per cent, silicon, the reduced losses which result from the use of this material being an important factor in obtaining the high efficiency of 98 per cent, reached by the machine on test. .... The rotor is of three-piece construction, and consists of a hollow central cylinder, to which two shaft-end pieces are secured. These three parts are spigoted together and secured by long, high-tensile steel links, which are shrunk in position, as will be clear from Fig. 102. The makers claim that the use of links, instead of bolts, for this purpose has the advantage that the stresses, and thus the forces holding the parts together, can be accurately checked by length measurements, both before and after shrinkage has taken place. In these particular rotors, the links are about 30 in. long, and when cooled down they hold the parts together with an axial tension of about 2,000 tons, thus giving great rigidity. The rotor also incorporates a brass cylinder of special construction, which is placed over and grips the end winding, so that the two slide together within the retaining ring when the winding expands owing to a rise in temperature. In this way, free relative axial expansion is provided between these two parts, without risk of damage to the insulation'.

The main 33kV switchgear was supplied by BTH.[5]

1938 'The eight Babcock boilers in the No. 1 station work at 450 lb. pressure and the six boilers of the same make in the No. 2 station at 630 lb., but the high-pressure units can feed the two lower pressure generating sets through reducing valve and, if necessary, 450 lb. pressure steam may be supplied to the higher pressure turbines, which must then naturally work at reduced load. The site is laid out for an ultimate capacity of 400,000 kW. .... From the steel flues the gases pass into downcast grit collecting chambers, where by reason of the large increase in diameter their velocity is reduced, thus causing most of the soot or grit which may remain in the gases to be deposited in the bottom of the chamber, whilst the slow-moving gases pass out at the side of the chamber into one of the concrete chimneys. A view of the chimneys and dust collecting chambers is given on page 472. Although each of these reinforced concrete chimneys, with a brick lining, is 335ft. high and weighs approximately 4400 tons, the rock foundation is so good that the excavation for the footing is only 1ft. 6in. deep. The thickness of the concrete at the point of gas entry is 11in. tapering to 6in. at the top. .... Not the least interesting feature of the two new Metropolitan-Vickers alternators (each rated at 50,000 kW C.M.R. at 0.75 power factor) is that they are wound for 33,000 volts.'[6]. The earlier units presumably generated at 7,250 volts.

1950 'Work on this station was begun in April, 1929, in a dock which was purchased from the Mersey Docks and Harbour Board, thus providing an excellent riverside site near the centre of the city’s electrical load. The station was designed by Mr. P. J. Robinson, the then city electrical engineer, for an ultimate capacity of eight 50 MW sets ; and it was expected that it would be completed in 1940-41. Two 51.25 MW sets, supplied with steam from four 160,000-lb. boilers at 450 lb. per square inch and a temperature of 750 deg. F., were completed in 1931-32; and a full description of the plant at that time appeared on page 37 and other pages of our 132nd volume (1931). Subsequently, four further boilers, each of 200,000-lb. capacity, working under the same conditions, were installed, thus completing the first part of the station. By 1938 a second boiler house, containing six 200,000-lb. boilers supplying steam at a pressure of 630 lb. per square inch and a temperature of 825 lb. to two 51.5 MW sets, were constructed. This extension was described on page 483 of our 146th volume (1938). By 1943, a second extension, consisting of one 250,000-lb. boiler and one 51.5 MW set, had been commissioned. This boiler, as well as those already in use, was stoker-fired. Mr. Robinson was also responsible for the extensions up to this date. In 1946, however, two 350,000-lb. pulverised-fuel fired boilers were placed in operation, and the station has now been completed by the installation of two 51.5 MW sets and three further 350,000-lb. pulverised-fuel boilers, bringing the final capacity up to 360 MW on a site area of only 11 acres, including the coal storage ground. The 1946 extensions were at first carried out under the supervision of Mr. J. Eccles, city electrical engineer from 1944 to 1948, but the work was taken over on April 1, 1948, by the British Electricity Authority. ...'[7]

1950 Work started on a further extension.

See Also

Loading...

Sources of Information